The roof pitch multiplier is the number you multiply a horizontal run by to get the length along the rafter. At 6/12 it is 1.118034, so ten feet of run is 11.18 feet of rafter. Roofers also call it the slope factor or the rafter factor. They are the same number.

Change the pitch

 

ROOF ANGLE 0.4636 RAD

26.5651°

PERCENT GRADE50.00%
SLOPE RATIO 1 : n1 : 2
RISE PER 126
RAFTER FACTOR1.118034

Multiply your run by 1.118034 for the rafter length. The cuts and the birdsmouth are in the app.

angle = atan(rise ÷ 12) atan(6 ÷ 12) = 26.5651° RISE PER 12 IN OF RUN

Multiplier by pitch

The last column is worked for a ten foot run, which is a twenty foot building span on a symmetrical gable.

PitchMultiplierGradeRafter over 10 ft run
2/121.01379416.67%10' 1-5/8"
3/121.03077625.00%10' 3-11/16"
4/121.05409333.33%10' 6-1/2"
5/121.08333341.67%10' 10"
6/121.11803450.00%11' 2-3/16"
8/121.20185066.67%12' 0-1/4"
10/121.30170883.33%13' 0-3/16"
12/121.414214100.00%14' 1-11/16"

Every pitch from 1/12 to 24/12 is on the full chart.

Where the number comes from

It is the hypotenuse of the pitch triangle divided by its base. For a rise of r over twelve, that is √(12² + r²) ÷ 12. Nothing about it depends on the size of the roof, which is why one number works for any run.

It is also why the multiplier is never less than 1. A flat roof would be exactly 1, and every pitch above that adds length.

Two things it does not include: the birdsmouth and the ridge deduction, and the tail. Multiply for the theoretical length, then take those off at the bench.

The pitch solved. The roof framed.